• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name Spayde

    Log entry time 20:24:44 on December 12, 2003

    Entry number 70848

    keyword=Run Coordinator Report for 12 December 2003


    Run Coordinator's Report - 12 December 2003 18:20


    General Comments/Problems/New Information

    Had some success in taking data on swing and owl shifts but were essentially without beam for all of day shift again. Some welcome news came out of the owl shift (see below).

    Problems

    New Information


    Past 24 Hours

    Swing

    Shift started waiting for beam while the MCC completed the daily G0 Beam Health Checkup and ran a 30 Hz PZT test (the test failed and further tests have been suspended pending a resolution). When beam was given to the hall Greg Smith commissioned the tungsten radiator (g0log 70699) while Paul and Dominique did DAQ test involving the 9th DMCH board (70745). The flyswatter had been put in during day shift access so we tried to take hour long runs on radiator+FS (successful) and LH2+FS (failed due to loss of beam). At this point the MCC began diagnosing problems with the chopper slit that eventually caused us to move to the Hall A chopper slit (elog 1185419). The flyswatter was removed and there was no more beam swing shift.

    Owl

    Beam came back at roughly 02:30 at which point Kaz was in to do RHWP/IA/PZT scans and start the beam feedback. A different approach was taken to setting the RHWP where essentially the position difference that we have little control over was minimized rather than the charge asymmetry (details are slightly more complex but that is the gist). We then took long feedback runs for the rest of the shift with very promising results (g0log 70795 and 70821). Over a period of about three hours we were able to control the position differences to less than 20 nm. These feedback runs were taken with the LH2 target in so we have some TE data on LH2. Unfortunately, these were the runs taken in "ts_scaler" rather than "ts_full" so there is no French time encoding or Fastbus data. Also attempted to take a long run on the radiator but were not allowed to do so by the MCC. The problem is that mentioned above; that by default the target in FSD position is LH2. Without resetting the FSD box it is necessary to mask the target FSD. This cannot be done without also masking the ion chambers and the magnet vacuum which is not a safe mode for the machine or the experiment to operate in.

    Day

    The day shift was lost to the switch from the Hall C chopper slit to the Hall A chopper slit. There appear to have been issues with coming back up from that. Also, as mentioned previously a couple of hours were lost due to the attempt to tune to incorrect nominal positions in the hall.


    Future Plans

    Friday Swing/Saturday Owl

    1. Deadtime studies that were punted from the previous swing.
    2. Another RHWP/IA/PZT scan followed by more long runs. This will be capped by another IA/PZT/RHWP scan to check stability of the calibration parameters.
    3. Time permitting the flyswatter will be put back in to get the LH2+FS data that were punted on the previous swing. Will take hour long runs at two magnet currents (5000 A and 4500 A).

    Saturday Day

    Moller Systematics

    Saturday Swing

    1. Deadtime studies.
    2. Another RHWP/IA/PZT scan followed by more long runs. This will be capped by another IA/PZT/RHWP scan to check stability of the calibration parameters.

    Sunday Owl

    Continuation of previous shift program or the CFD threshold program necessary for Q2 and centering.

    Sunday Day

    Hall A energy spread minimization will be going on so there will be no beam. We will use the opportunity to access the hall for GMS checkout and TLD removal.

    Sunday Swing

    1. Halo target centering
    2. Halo monitor calibration
    3. Target density test