Run Coordinator Dayly Report (29-30 April)RC Report, Wednesday
April 28rcreport_22apr04.html
Run Coordinator Daily Report for 11 May Owl to 12 May Swing
Summary
Beam came really back this morning at around
02:00.
We took alternate HallC ON/OFF data until 08:00 with HallA
ON.
HallA went off at 08:00 as scheduled but due to beam studies
we only got the beam in HallC around 09:30.
MCC gave us the missing 1h30' without Hall A until 17:30
HallA is now back albeit at low current (<10 uA).
GMS is still off.
Significant News
-
Following today MCC meetings, the schedule is the following:
Leakage Runs without HallA:
-Wed Day (completed)
-Thu Day
-Fri Day
-Sun between 04:00 (4am) and 12:00 (noon)
This is not the best time for us but there has been some fight
with
HallA and B (and within them) as we have all conflicting
requirements
(HallA wants to go to 2-pass which switches off both B and C, HallB
wants to change target and requires additional calibration runs).
That compromises transverse running (we can keep it on the
books
in case HallA would suffer a serious breakdown before Sunday)
but we are thinking with Doug Beck of ways out..
-
During the next 24 hours we will have 2 shifts with HallA+B ON followed
by 1 shift (starting tomorrow at 08:00 of Hall B+C leakage.
-
For Wednesday Swing and Thursday Owll we will run the
reduced
program with HallA and HallB ON as shown in the detailed run plan
below.
-
During Wednesday Day, we'll follow the more complex program with
HallA OFF as outlined below.
Short term Plans
Wed 16:00-Thu 08:00
HallA
and Hall B are ON
-
Take a Moeller measurement with
IHWP=IN
-
Switch IHWP
IN==>OUT
-
Take another Moeller
-
Set feeback
-
Start production runs with
IHWP=IN.
Alternate 2 types of runs with
HallC
ON and OFF with the following settings:
- Reference_FiB_Buddy
- NA thresholds to 7 and FR thesholds to
50mV
Set lumis to low gain
-
Switch to standard lumi HV file
HV.2004-02-19.lumi_halo_on.hvc
-
Set the 6 lumi amplifier settings in Electronics Shack
upstairs
to low gain : 10^5 and 10 uA/V
(if you don't know how to do,ask the RC or another
knowledgeable
person).
-
Hall C ON, 40 uA, set the feedback
-
Take a 1h run
-
Set lumis to high gain
-
Switch from standard lumi HV file
HV.2004-02-19.lumi_halo_on.hvcto
HV.lumi_highhigh_on.hvc
-
Set the 6 lumi amplifier settings in Electronics Shack
upstairs
to high gain: 10^6 and 1 uA/V
-
Hall C OFF (Laser off, slits wide open),
-
Take a 10' run
Alternate runs with HallC ON and
OFF
Thu 08:00-16:00 HallA
OFF and Hall B ON
DON'T FORGET TO RESET LUMI TO LOW GAIN WHEN
BEAM IS SENT TO HALLC
Longer term Plan
-
Leakage studies likely to continue until Friday Day + Sun
04:00-12:00
-
To be followed by detector tests? (could also be done on Fri
Swing)
-
Transverse running becomes highly hypothetical
Concerns
Don't forget to register
tomorrow
to Run-Around
JLab Race. If you are on shift, look for a non-racing mate to replace you
around 15:00-16:00. There will be special exemptions for the Analysis
Workers
and the RC :-)