    User name arvieux

    Log entry time 22:34:27 on May 07, 2004

    Entry number 84408

    keyword=RC Daily Report 6-7 May

    Run Coordinator Daily Report for 6 May Owl to 7 May Swing

    Summary

    Completed detector studies with SOS  (08:00-17:00)
    After the detector  studies we experienced multiple SMS fast dumps starting at 18:25 on Wednesday and lasting until 05:00  on Thursday Owl..
    Faulty component (CPU) was replaced on Thursday morning and magnet was back to full current at  11:00.
    A quick test aiming at measuring the leakage from the separator was performed with Hall A/B at full current and Hall C slits fully closed.
    The rates were similar to green block rates (no leakage from taht source). No analysis (and g0log) yet on these results.
    Then we switched to target boiling studies by Greg and Lars. They were apparently successfull (?) but there is nothing in g0log except that the target
    was moved IN at beginning and moved OUT at the end.
    Started then the completion of the threshold studies with IHWP=OUT (presently running). These will most likely request another shift after the laekage studies of tonight.

    GMS is still off.
     


    Significant News


    On Wednesday we have had a meeting with injector and accelerator experts to draw a test plan for further leakage studies. We came to the conclusion
    that we needed several periods without Hall A running:

    During a meeting with Larry Cardman and Dennis Skopic and we got approved for the first 2 tests  (8 hours in total) and scheduled for
    Friday Owl (00:00-08:00)

    At 17:00 Hall C was closed and we started putting things back to normal running conditions.

    At 18:25, SMS fast dumped. Kaz and Damon were called but they experienced difficulties with  one analog input modules.
    After they fixed the problem,  SMS quenched again at 22:45 and at 03:16. At that point we decided to wait until Thursday for consultation of magnet experts.
    The faulty component  (a CPU) was changed during the morning and magnet was back to full current at  11:00.
    The leakage studies are postponed to Saturday Owl, with the approval of JLab management.

    Target boiling studies completed
     

    Short term Plans

    SETTINGS TO BE USED WHEN RUNNING WITH NO CURRENT IN HALL C

    Longer term Plan


     
     
     
     
     
     
     
     

    A copy of this log entry has been emailed to: beck