    User name spwells

    Log entry time 16:39:30 on April 06, 2004

    Entry number 81598

    keyword=RC report for 5 April Swing through 6 April Day

    Run Coordinator's Report for 5 April Swing to 6 April SwingSummary

    Beam studies occupy most of swing shift. Fro 18:00 through 23:30 beam not delivered to Hall C. Injector tuning for 3 Hall operation, along
    with accelerator interlock problems (related to Hall A?) responsible for down time. At end of swing shift, Reza gets reasonable injector tune
    for 40 uA for Hall C, and 100 uA for Hall A. After beam returns, LH2 production running through owl and day shifts.
     
     
     


  • Significant News


    Plans

  • MCC will take beam from 17:00 until 22:00 for beam studies/injector setup.
  • After beam is back into the Hall, start taking LH2 production data. CHECK THAT IA/PZT FEEDBACK IS CONVERGING AND IS OPERATIONAL! If not, run a RIP scan to get new feedback parameters and get the feedback to work satisfactorily.
  • Continue with LH2 production running through Owl shift.
  • Moller measurements and IHWP removal tomorrow evening. Given the personnel on shifts for swing and owl (Sarah and Kaz, respectively), we will wait until around 20:00 to perform the Moller measurements and remove the IHWP. AFTER THE IHWP STATE CHANGE, A rhwp SCAN SHOULD BE PERFORMED TO ZERO OUT THE CHARGE ASYMMETRY IN THE HALL. If, after this change, feedback is not operational, Kaz will be on shift to make it work.
  • After Moller, continue with LH2 production running.


  • Concerns