Main INDEX
Monthly INDEX
PREV
NEXT
User name J. W. Martin
Log entry time 17:02:30 on March 10,2004
Entry number 79057
keyword=G0 RC summary for Owl shift Monday, March 7 --- day shift Wednesday, March 10 2004
RC Summary
Monday, 8 Mar. owl
through
Wednesday, 10 Mar. day
- Beam off for maintenance period. Target warm and no shifts staffed.
Achievements and events
Plans
- We are down for a maintenance period until (at least)
Thursday swing. Update on task list:
| Task | G0 Responsible | Work | Done |
|---|
| Install TLDs | McKee/Martin/Williamson | 50% |
|---|
|
| Replace IOCSE20 | Williamson | MCC(?) | 100% |
|---|
| Install more green blocks. (?) | Hall C | 100% |
|---|
|
| Resolve "SMS PLC crash/freeze leads to fastsump" | Williamson | | In progress |
|---|
| SMS/target (?) vacuum pump maintenance | Spayde | Brindza | |
|---|
|
Position/Energy modulation coil
checkout/maintenance | Rutledge | 100% |
|---|
| G0 harp signal noise | Williamson | | in progress |
|---|
| Harp PMTs connect/checkout HV and signals | Vulcan | |
|---|
| Install Halo 7,8 | Phillips | | 90% |
|---|
| Fix BPMs C07, C20 | Pitt | P. Francis | in progress |
|---|
| Pivot BPM noise resolution(?) | | | |
|---|
| Vacuum photodiode | Pitt | 100% |
|---|
|
| Laser phase noise | Nakahara | Poelker/Graims | 100% |
|---|
| Laser circular polarization | in progress |
|---|
|
| Musson box timing issues | | Musson | 99% |
|---|
| FastSEE software issues | | Dickson (?) | |
|---|
|
| Channel 16 HV cable move and software fixes | Breuer | 50% |
|---|
| CHC UPSs | Vulcan | 100% |
|---|
|
| Survey SMS vs. FPDs (?) | Roche | | |
|---|
|
| Recovery plan | Martin/King | in progress |
|---|
- My impression of the recovery and run plan for the next few days:
- Plan to cool down target 3/11 afternoon.
- On physics beam back (expected 3/12 4 pm) 1 shift beam checkout.
- Weekend: longitudinal running on LH2.
- Monday, 9 am: Hall C spin dance (decided at today's weekly PD meeting).
Leave Wien angle at best transverse setting and begin transverse running
(about 4 days according to Paul King's plan).
Concerns and Their Resolution
- Spikes in the French timing spectra appear from time to
time. Still under investigation by Jacques with analysis by Sarah.
- Hope to resolve G0 BPM and harp issues by simply running harps
at higher current (40 uA CW possible, relayed by Vulcan from Yan, as
the wires are carbon). Williamson still diagnosing harp noise.
- Williamson working on design of magnet power supply off
at full power without causing fast dump and without
compromising quench protection.
- IOCSE20 replaced.