    keyword=RC Summary Tuesday 02-24-2004 Swing through Thursday 02-26-2004 Day

    RC Summary Tuesday 02-24-2004 Swing through Thursday 02-26-2004 Day


     Achievements
    The plot below illustrates how data taking on LH2 has been going.  Each vertical bar (except the last one) represents a 24 hour day (midnight to midnight).  The last bar terminates at the end of the day shift today.  Each bar is divided into colored sections according to the time allocated to particular activities.  Data was provided by Julie's "abu" program which relies on information stored in the analysis data base, by the "beam accounting" program (for Beam Not Available (BNA) and Beam Available but Not in Use (BANU)), and the log book for Moller running.

    The purple "Other" sections include relatively infrequent activities (BPM/BCM calibrations, harp scans, high voltage calibration, beam energy measurement, etc.).  For example:
    "Other" also includes unavoidable "overhead" such as the time to stop and start runs and possibly some mislabeled BANU time.
    How the beam was used...

    120 Hz running has not appeared in this plot since 02/24 due to a problem with the reporting of that data by Julie's abu program.

    Plans

    Concerns and Their Resolution

    List of shift summaries

    Tuesday 02/24 Swing and ABUs
    Wednesday 02/25 Owl and  ABUs
    Wednesday 02/25 Day and ABUs
    Wednesday 02/25 Swing and ABUs
    Thursday 02/26 Owl and  ABUs
    Thursday 02/26 Day and ABUs