    keyword=(delighted) RC Summary Sunday/Monday 02/16

    Run Plan Friday 02-06-2004Run Plan - Wednesday 01-28-2004


    RC Summary Sunday/Monday 02-16-2004

        A good (excellent?)  day of data taking !


     
    Achievements during this period:


    1) Beam at 40 uA and running with 6 mm halo target

    2) IHWP is now IN (IHWP-IN)

    3) Feedback operation and beam parity quality

        - Data continues to look pretty good (see Feedback)
        - New slope adjustement performed (see Slope-Adjust)

    4) 120 Hz are being replayed by the worker (120Hz)
        - OK, so 120 Hz only every 8 hours.

    5) Observed IN+OUT asymmetry for present (Feb) LH2 data is
        about compatible with 0 (see IN+OUT). 

    6) Data files recovered (see EPICS)

    7) Database update (Database)

    8) Slopes for beam parameter correction (Beam-Correction)

    9) Coil modulation small problem is fixed
    (see Coil and ...
        (the whip sound did not work on... Gary) e-log to come)
        Also change the run plan to account for short trips
        (no need to re-run the script in this case)

    10) Halo is of the order/smaller than 1 ppm outside of the 6 mm hole
         (see Halo)

    11) Substantial increase of effciency in data taking (8 to 12 hours/day)

    On a more general basis. Mid-Term plan

    1) We will likely change the IHWP state on Tuesday (2/17)
          Make a RIP scan just after, and a Moeller measurement before and after


    2) Fastbus measurement to perform a check of the gain and
        set a reference spectra. Tentative : Tuesday 2/17 after beam development


    3)  BPM/BCM calibration need to be done every week. Tentative next Wednesday.
         Mark has asked for a gain change in BCM1

    4) Lumi scan on LH2 (asked by Silviu and Jianglai). After BCM calibration.



    Concerns

    A) PMT Gain calibration

    D) Beam trip is still hurting us ...

    C) ... as well as magnet in ARC 6

    List of shift summaries
     